Royal Mail Group, Midlands

Industrial · Mail centre refurbishment

JYM were appointed by Royal Mail Group to deliver a significant programme of upgrade works to a mail and parcel sorting facility in the Midlands, acting as Project Manager, Building Surveyor and Principal Designer throughout.

Parcel sorting facility in the Midlands refurbished for Royal Mail Group
Client
Royal Mail Group
Sector
Industrial
Services
Project Management, Building Surveying, Principal Designer
Status
Completed

Upgrading a sorting facility that never closes

Works were carried out across the site and included:

  • Replacement of the fire alarm system
  • Replacement of the CCTV installation
  • Replacement of dock levellers and traffic doors
  • Installation of new high-speed doors
  • Replacement of personnel doors
  • Installation of bird netting
  • Replacement of the passenger lift
  • Refurbishment of staff shower facilities
  • Replacement of external yard drainage
  • Roof repairs
  • Repairs to operational yard surfaces
  • Replacement of the vehicle weighbridge

The main challenge was keeping the site running, as it operates 24 hours a day, seven days a week. The works were carefully programmed and phased to keep disruption to a minimum.

All works were delivered on time and within budget.

Gallery

Project photography